This engagement focused on Health and Safety, Production Management and Mine Planning services.
As part of the mine planning requirement, VBKOM conducted a LOM investigation of the economic potential of the mining project. The mine planning cycle included Pit Optimisations, Mine Designs, Mine Production Schedules, an Equipment Study, Cost Modelling, and a Mineral Reserve Estimation.
The work programme covered the technical activities necessary to complete the stated assignment and consolidate the available information into usable project outputs.
The approach was applied within the context of Diamond mining in South Africa, keeping the project-specific operating and study environment central to the assessment.
Technical inputs, assessments and deliverables were coordinated throughout the assignment to maintain consistency and alignment with the defined project objectives. The work was undertaken with due consideration for the intended application of the results, with findings captured through structured and traceable documentation. Collectively, the completed outputs provided a coherent technical basis for client review and supported informed consideration of subsequent project activities, decisions and development requirements.